From late December 2017, we had been packing and preparing for the big removal.
Meanwhile, we were rushing to finish painting the floor in our new factory plant.
The big day had come on 3rd January 2018, when some 13-meter long large trucks came in to pick up our heavy machines.
Quicker than we had expected, it took 5 days to have most of our equipment moved to the new factory plant.
The old factory plant was left like a mess, haha.
One the other hand, the new factory plant was not much better, with stuffs and machines unloaded and jamming all the space.
Luckily, we are all dedicated staff and it only took us several days to arrange the equipment and belongings at the new location. We resumed production two days after we had arrived.
Then we had a two-week off for the Chinese New Year. With one and a half month’s repairing and maintaining, and doing the office decoration after we came back in mid-February, we are now better than ever. Also, at the new location, we can hire more workers. Thus, we’re looking into a very promising and productive year of 2018!